Lawsuit
ties up plan for coal plant near Great Falls
By
MATTHEW BROWN
Associated Press
Construction
of a coal-fired power plant near Great Falls will be delayed pending resolution
of a lawsuit that challenged the project's $650 million federal loan request,
the project's general manager said Wednesday.
The
setback for the Highwood Generating Station, a 250-megawatt facility that would
be the largest coal plant built in Montana in two decades, follows action by
three Montana cities to reject the power it would provide.
The
city of Great Falls, with a 15 percent stake in the plant, had attempted to
solicit Missoula, Bozeman and Helena as future Highwood customers. But elected
officials from the three cities recently rejected the offers following
complaints from residents and environmental groups opposed to greenhouse
gas-producing coal plants.
"There
was quite a bit of reaction from the public saying, 'Let's please look at other
alternatives,' " said Missoula city spokeswoman Ginny Merriam.
Across
the country, plans to build new coal plants have encountered opposition in
recent months because of their potential to exacerbate global warming. A
lawsuit filed in July by three environmental groups sought to scuttle the U.S.
Department of Agriculture loan program that would finance construction of
Highwood and at least six other plants nationwide.
Loans
for those facilities could top $5.1 billion, including $650 million for
Highwood, according to the Rural Utilities Service, the USDA division that
manages the loan program. The funds would cover 85 percent of the Highwood
project's costs.
The
utilities service in May gave initial approval to Highwood following an
environmental review of the project. The review did not include greenhouse gas
emissions because those are not regulated by the federal government.
The
plant would be built by the Southern Montana Electric Cooperative and provide
power to customers throughout southern and central Montana. Backers of the
plant say it would meet growing demand for electricity in Montana and across
the West. A coal plant was chosen as more cost-effective and reliable than a
wind farm or natural gas plant.
On
Wednesday, SME general manager Tim Gregori said construction could not move
forward until the lawsuit over the loan program is resolved.
"It
is our understanding that the legal challenge ... will have to be resolved
before the loan becomes final," Gregori said. He said the project
"will move forward as a function of financing."
SME is
not a party in the lawsuit, which named as defendants Agriculture Secretary
Mike Johanns, Rural Utilities Service Administrator James Andrew and Richard
Fristik, an environmental specialist with the agency.
The
Rural Utilities Service referred questions about the financing delay to the
U.S. Justice Department, which is handling the lawsuit. A Justice Department
spokesman, Andrew Ames, declined comment.
No
hearings in the lawsuit have been scheduled. Plaintiffs include the Sierra
Club, Citizens for Clean Energy and the Montana Environmental Information
Center.
Highwood's
air quality permit from the Montana Department of Environmental Quality also
has been challenged by environmentalists. A hearing on that matter before the
state Board of Environmental Review is set for January.
Additionally,
the project lacks the necessary zoning permissions from Cascade County, which
approved the project but later rescinded that approval as part of a countywide
review of its zoning policies.
"There
are all sorts of indicators this thing is in big trouble," said Anne
Hedges with the Montana Environmental Information Center. "We've had a
series of successes in the last couple of weeks that indicate Montana isn't
interested in dirty power."
Great
Falls City Manager John Lawton said the rejection of electricity from the plant
by Bozeman, Missoula and Helena would not undermine the city's share of the
project's finances. He added that Bozeman's action came after that city was
given some preliminary information but before final details could be offered.
"If
they don't want it, that's fine," Lawton said.
Gregori
described the multiple obstacles faced by the plant as temporary and expressed
confidence it would be built.
"It
isn't a matter of, 'If it's delayed to a certain point we stop,' " Gregori
said. "It doesn't change the reason for doing it, it just means we are
delaying how quickly we can reach our goal."