Article
published May 12, 2007
Coal-fired power plant gets green light
By KARL PUCKETT
Tribune Staff Writer
State
and federal regulators on Friday gave two thumbs up to plans to construct the
state's seventh coal-fired power plant outside of Great Falls.
"It
was a good result for the project and, I think, a good result for the
public," said John Lawton, city manager for Great Falls, which is a
partner in the facility.
Opponents
of the project, however, gave the rulings a thumbs down, and vowed to continue
fighting the proposed Highwood Generating Station.
The
$720 million plant would produce 250 megawatts of power and serve up to 120,000
rural electricity customers from Great Falls to Billings.
The
favorable "record of decision" for developer Southern Montana
Electric Generation and Transmission actually contained two major decisions:
The
U.S. Department of Agriculture's Rural Utilities Service agreed to fund the
majority of the construction cost Ñ assuming the specifics of SME's loan
application are approved in the coming months.
And the
state Department of Environmental Quality agreed to issue a final air-quality
permit, which the plant needs to operate.
RUS and
the state DEQ jointly issued the decisions, which do not guarantee the plant
will be built.
But for
those who support the plant, they were critical victories in the march toward a
groundbreaking.
The
remaining regulatory hurdle is a federal decision on the loan guarantee to
finance construction.
"It's
one of the steps we go through in getting ready to reach a decision on loan
approval," Jim Newby, RUS's assistant administrator of electric programs,
said of Friday's decision.
Now
that RUS officials have agreed in concept to fund the project, federal
officials will go to work evaluating specifics of the project's financial and
engineering feasibility.
That
process will take a couple of months and will precede a decision on the loan
guarantee, Newby said.
The
environmental review of the project found the power plant would not have a
significant environment impact, said Jim Andrew, administrator of RUS. He also
noted that most of the power from the new plant already is committed.
For
him, both were key issues to consider before signing the record of decision.
"With
all those factors together, it just seemed feasible to me," Andrew said
from Washington, D.C.
The
consortium of five rural cooperatives that make up SME is seeking a loan from
RUS to cover 85 percent of the estimated cost of $720 million, while the city
of Great Falls is planning to pay for the remaining 15 percent.
The
previous split had been 75-25.
SME CEO
Tim Gregori said the change is because of revised load forecasts showing the
five co-ops now need 213 megawatts of power, which would reduce the dedicated
allocation for Great Falls to 37 megawatts.
But
Lawton said the city still would be able to buy additional power from the
plant, if necessary. The city's utility arm, Electric City Power, provides
power to larger governmental and industrial customers, but not residents.
The
final air-quality permit requires SME to install additional mercury-control
equipment above and beyond its regular pollution controls, said Dave Klemp, the
DEQ's permitting program manager in the agency's permitting and compliance
division.
Klemp
said one of the biggest complaints the DEQ received from the public was that
the mercury-control equipment wasn't included in the draft permit.
"It's
going to add some extra expense (to the plant), but it's not uneconomical from
our perspective," Klemp said.
Gregori
said SME was planning to use the "activated carbon injection"
mercury-control equipment anyway.
The
public has 15 days to appeal the air-quality permit decision, Klemp said.
Friday's
decision drew a quick reply from opponents, who have criticized the facility
over emissions even as the developers have touted the plant's state-of-the-art
pollution-control technology.
"We
feel very confident this is never going to happen," said Charles Bocock of
Citizens for Clean Energy.
He
predicted that lawsuits he expects to be filed in response to the decisions
would shine a spotlight on what he described as RUS' ineptness in reviewing the
project.
Anne
Hedges of the Montana Environmental Information Center said MEIC would appeal
the air-quality permit decision.
She
also said lawsuits were "probable" against the state for the
air-quality decision and the RUS for its environmental review of the project.
She called the record of decision a "pathetic excuse" for a decision.
"RUS
has been ignoring the concerns of the public for almost a year," Hedges
said.
One of
the environmental organization's largest concerns is the emission of greenhouse
gases. According to the environmental impact statement, Highwood would emit
about 2.8 million gallons of the gases Ñ linked by scientists to climate change
Ñ yearly.
Gregori,
however, said the decision affirmed the need for the plant to provide
electricity and also that it meets all applicable state and federal
environmental regulations.
He said
the DEQ and RUS did yeoman's work. He added that he is expecting a legal
challenge.
"When
we started this process, we realized it was a significant undertaking that
would have many peaks and valleys," he said.
RUS
officials say they want the National Park Service and SME to reach an agreement
on mitigating the proposed plant's impact on the historic Lewis and Clark Trail
before funding is released.
A
portion of the trail, a National Historic Landmark, is within view of the
plant.
Even without a mitigation agreement, Newby said RUS has the authority to fund the project. The record of decision says "additional stipulations" resolving potential adverse effects to the Great Falls Portage National Historic Landmark are being negotiated.