Article
published Aug 12, 2007
Why not wind instead of coal?
By RICHARD ECKE
Tribune Staff Writer
Critics
of the proposed Highwood Generating Station have been saying for months that
wind power could eliminate the need for the coal-fired plant.
The
theme runs through public meetings, letters to the editor, online forums and,
most recently, a lawsuit filed to block federal funding for the $720 million
project east of Great Falls.
So
the question, posed recently to several people on both sides of the debate, is
"why not wind?"
The
short answer is that it would be possible to substitute wind power for
electricity from the coal-fired plant if it were supplemented, or firmed, by
electricity from other sources such as hydroelectric power or natural gas-fired
power plants.
Standing
in the way are technical issues and the rising costs of wind power.
In
addition, the five rural co-ops comprising the Southern Montana Electric
Generation & Transmission Cooperative need new power quickly to replace
power they are losing from the Bonneville Power Administration.
Great
Falls City Manager John Lawton, who has taken a lot of heat over the city's
participation in the Highwood project, said he believes in wind power but that
it is unlikely to be the total answer.
"It
has to be available and it has to be the right price," Lawton said.
He
added that the city of Great Falls will soon issue requests for proposals from
wind-power companies and natural gas-fired plants to determine what other power
sources may be available for the city's Electric City Power arm.
But
Lawton said he sees such power as a supplement to the 250-megawatt Highwood
Generating Station, not a replacement. He added the city plans to continue to
pursue owning 15 percent of the coal-fired plant.
Rural
Utilities Service criticized
Critics
contend that the federal Rural Utilities Service, which is considering lending
Highwood project developers more than $600 million, appeared to blow off wind
as an alternative in a May 10 record of decision it issued jointly with the
Montana Department of Environmental Quality.
The
record of decision and final environmental impact statement states that wind
energy would be "incapable of providing approximately 250 (megawatts) of
base load due to its intermittency."
Other
plant backers have rapped wind as either impractical or too expensive.
Critics,
including the Montana Environmental Information Center and the Sierra Club, say
Highwood developers should have thought about buying wind energy instead of
burning coal.
They
raised the issue in a federal lawsuit filed in Washington, D.C., this summer.
The third plaintiff was the Great Falls-based Citizens for Clean Energy.
Neil
"Jerry" Taylor, a member of the citizens group, maintains city
officials should have explored wind power "two years ago."
"I
don't think they explored the possibilities," he said. "They haven't
done their homework."
Taylor
said his group has been pushing wind power for more than a year.
"Nobody
listens," he said.
Wind-power
advocate and Cascade County Commissioner Peggy Beltrone contended that the
Rural Utilities Service and the Highwood plant developer have been so focused
on coal that wind has been given short shrift. Beltrone said part of the reason
the federal agency dismissed the idea of wind power is because it "has
only dealt with co-ops using coal."
Wind
power pioneer Ed DeMeo, president of Renewable Energy Consulting Services of
Palo Alto, Calif., couldn't agree more.
DeMeo
said recently that he hopes developers of the proposed Highwood Generating Station
east of Great Falls "won't take what they see as the easy way out and
build another coal plant. I think they should seriously consider wind."
Kenneth
Reich, a Boston attorney for SME, counters that the impact statement on the
plant "does a pretty good job of considering the wind option." He
added that the analysis was thorough and detailed.
To
create enough wind to equal the Highwood station's output would require 18.6
square miles of land, covering 11,880 acres, the impact statement said. Reich
noted SME already has been criticized for its plan to place four wind turbines
near the coal-fired plant.
Wind
power getting pricier
Taylor
and others have been weaving a tantalizing tale of late, describing how cheap
wind-generated power is from Montana's biggest wind farm at Judith Gap.
That
farm is a success story, thought it has created some technical challenges for
NorthWestern Energy, which serves about 320,000 electric and gas customers in
Montana.
"We're
very pleased with Judith Gap," NorthWestern spokeswoman Claudia Rapkoch
said.
One
of the keys to the farm's success is "Montana has super-strong wind,"
said Mark Jacobson, senior development manager for Chicago-based Invenergy
Wind, which owns the Judith Gap farm.
General
Electric, which supplied wind machinery to Judith Gap, considers Montana's wind
to be something special, he said.
"Judith
Gap produced more electricity than any other wind farm in North America within
their fleet," Jacobson said.
NorthWestern's
decision to purchase wind power from the 135-megawatt Judith Gap farm was
far-sighted. Wind power from Judith Gap now costs the company between $42 and
$46 per megawatt hour, after figuring in the costs of supplemental power.
That's a bargain-basement price with default electricity prices exceeding $55
per megawatt hour.
Jacobson
said his company would be happy to talk to SME or Great Falls officials about
selling wind power to them. He said the wind farm expects to expand by 53 or 54
megawatts as soon as 2008.
"It
is a possibility," Jacobson said. "We're talking to a number of
people right now. There are no signed contracts. We'd be happy to get together
a proposal."
Jacobson
declined to discuss the cost of new wind power from Judith Gap. But
conservation groups claimed in their recent lawsuit that firmed wind power from
central Montana could still be had for no more than $45 per megawatt hour.
Lawton
called the claim "ridiculous," saying the price of wind power has
risen since 2005, when NorthWestern Energy agreed to buy wind power from Judith
Gap for 20 years at about $31 a megawatt hour. Supplemental electricity, known
as firming power, pushes the total cost to $42 to $46 per megawatt hour,
according to Rapkoch.
She
said Montana consumers get that wind power from NorthWestern at cost, with no
markup.
Unfortunately
for groups such as SME that are hunting for energy, wind power costs are
soaring.
Lawton
said the city would be happy to snap up wind power at the old price.
"Will
they sell it to us now for $42?" Lawton asked.
Coleen
Balzarini, the city's fiscal officer, said she talked to Jacobson last month
and was told the 53 or 54 megawatts of wind power would cost more than $50 per
megawatt hour, not counting the firming power. With that added in, it could
push the total cost higher than $60 per megawatt hour, which is more than
NorthWestern's August residential default power cost of $56.87 per megawatt
hour.
The
Highwood project environmental impact statement estimated the cost of firmed
wind power at $66.24 per megawatt hour.
That's
substantially higher than the latest estimate of about $50 per megawatt hour
for power from the proposed Highwood Generating Station. However, several
unknowns exist that are likely to push up that cost.
Opponents
of the coal-fired plant contend an expected federal carbon tax, which will tax
companies based on carbon emissions, will increase Highwood's final power
price. They also say the cost of power from the Highwood plant will increase if
SME attempts to capture carbon dioxide and ship it via pipeline to oil fields
in Canada or bury it underneath a salt dome east of Glacier National Park.
Last
week, two Great Falls city commissioners said they think the wind versus coal
issue is more complex than wind advocates portray it.
"This
thing sounds so simple that you'd be doing it tomorrow," said City
Commissioner Bill Beecher. "There's a catch someplace there."
Lawton
said two major stumbling blocks for wind are cost and availability. He said it
makes no sense for the city and SME to cancel plans for the Highwood station
and "chase a ghost" Ñ wind power.
He
added the Judith Gap wind farm did not exist when rural co-ops began planning
to make up for a loss of cheap Bonneville Power Administration electricity that
is scheduled to start in 2008.
Base
load vs. firmed wind
Officials
sometimes dismiss wind as an unpredictable source of energy.
"If
it's base load, then wind just simply can't do it," said Jason Hayes,
communications director for the Washington, D.C.-based American Coal Council.
That's a view echoed by Great Falls Mayor Dona Stebbins.
"The
problem with wind power is that it doesn't supply base load," Stebbins
said.
A
base-load facility is one that provides a steady source of power.
Most
energy experts agree that Hayes and Stebbins are right in saying wind alone
cannot provide all the power needed by a community or rural electric co-op.
But
the experts also say it's possible to substitute wind for coal, if it's
supplemented by firming power from other sources.
"The
firming power is the big thing," Hayes said.
Wind
power from the Judith Gap area is being firmed relatively cheaply, and wind
supporters argue that firming power ought to be available for more Montana wind
farms, albeit at increasingly higher prices.
Greg
Jergeson, chairman of the Montana Public Service Commission, agreed that
electricity generated by wind can serve as base-load power if it's properly
firmed.
"Firming
is getting more expensive," Jergeson added.
Power
to firm the 135-megawatt wind farm at Judith Gap comes primarily from contracts
with two neighboring utilities, Idaho Power Co. in Boise, and Spokane-based
Avista Utilities.
"They're
both primarily hydro( power) utilities," Rapkoch noted. Water power can be
well-suited to firming wind because water can be stored behind a dam, then
released to create power when it's needed.
Another
way to firm wind is through a natural gas-fired power plant. The down side to
gas is it's expensive.
NorthWestern
Energy arranges for its own firming power for Judith Gap. Great Falls officials
say they'd be forced to go out and find their own firming power if the city
purchased new wind power from Judith Gap or elsewhere.
Rapkoch
confirmed that would be the case, adding it probably wouldn't be easy for Great
Falls to buy firming power.
"It's
not easy for us right now," Rapkoch said.
Contracts
with Idaho Power and Avista are expiring soon, and NorthWestern is finding the
market "very challenging," she said.
"The
potential resources out there are drying up," Rapkoch added.
Montana
in tough spot
Montana's
position in the energy picture is a difficult one, according to DeMeo.
The
electrical grid system is quite inflexible, with few connections to outlying
areas, and few sources of power Ñ primarily coal-fired power from Colstrip and
hydro-electric power from dams in Cascade County and elsewhere.
Rapkoch
agreed. She said that's why NorthWestern Energy hopes to build a new source of
generation, probably a natural gas-fired power plant that could firm wind and
cover short periods of peak electricity demand. The utility also has proposed a
new transmission line from roughly Townsend to southwest Montana and into
Idaho.
Another
transmission line, called the Alberta Tie project, has been proposed from Great
Falls into Alberta.
Wind
will help diversify Montana's energy supply, but Rapkoch said there's a limit
to how much wind NorthWestern could handle. That's why NorthWestern is taking part
in a new study with wind experts and others that should pin down how much more
wind power the system will accommodate. That study is due out by the end of the
year.
Some
common ground exists
Hayes
conceded that coal has an image problem these days, although he pointed to a
new plant near Edmonton, Alberta, Epcor's Genesis III plant, which is a
"supercritical" facility that burns cleanly yet produces inexpensive
power, he said. He argued that new technologies including gasification,
supercritical plants, coal-to-liquids and other approaches will give coal a new
lease on life.
Taylor
argues that if Great Falls-area residents could choose between a coal-fired
plant and buying power from a wind farm, he thinks they'd choose wind.
"It's
a no-brainer," he said.
Wind
power is not immune from criticism. The turbines kill birds and bats, and some
people think huge wind farms don't do much for the landscape or view.
Texas-based
Wind Hunter LLC originally planned to erect 337 towers in a 500 megawatt farm
30 miles northwest of Glasgow, but after objections from environmentalists
about its proximity to a wilderness study area, the farm was scaled back to 114
of the 390-foot-tall machines.
Wind
energy pioneer DeMeo said utilities tend to be conservative businesses, bound
by tradition.
"Their
job is to keep the power flowing," he said. DeMeo added that utilities
need incentives to turn toward renewable energy. A carbon tax, which DeMeo
believes is coming, will be one way to do that.
If
the Highwood Generating Station becomes a test site for carbon dioxide capture
and storing, it could be a good thing, DeMeo said. However, he said carbon
capture and sequestration may come into play more often when retrofitting old
plants rather than building new ones.
DeMeo
said it's not unreasonable to expect the United States to get 20 percent of its
power from wind in a few decades, but he conceded wind won't be a complete
solution.
SME
attorney Reich said much-need new power needs to come from somewhere, and price
remains a big selling point for coal.
"In
the next 10 years or so, there's going to be a severe energy shortage in all
parts of the country, including the Northwest," Reich said.
The
coal council's Hayes agreed and said he doesn't think that need for new power
should be broken down into coal versus wind.
"We're in it together," Hayes said. "We need the electricity. Demand for electricity is going through the roof."